North American Palladium Commences Development of Canadian Mine

North American Palladium Ltd. is pleased to announce that its Board of Directors has approved the development of an underground mine at the Company’s Lac des Iles operations. The decision to proceed with an integrated open pit and underground mine project was based on a full feasibility study prepared by Roscoe Postle Associates Inc. of Toronto, Ontario.

NAP currently operates an open pit mine and mill at Lac des Iles with a design capacity of 15,000 tonnes per day. In late 2003, the Company commissioned a full feasibility study in response to scoping studies and a pre-feasibility study that indicated a higher grade sub-vertical ore body located directly beneath the open pit mine was a viable underground mine. The underground feasibility study defines, as its base case, a nominal 2,000 tonnes per day mechanized longhole stope mine accessed through a portal in the Lac des Iles open pit with an initial mine plan containing 3,542,000 tonnes of Proven and Probable Reserves.

These underground reserves contain approximately 6.62 grams of palladium per tonne at a cut-off grade of 4.5 grams per tonne. In addition, these reserves contain approximately 0.40 grams of platinum, 0.34 grams of gold, 0.07 percent copper, and 0.08 percent nickel per tonne.

The integrated production plan for the expanded Lac des Iles mine calls for the blending of higher grade underground ore with that of the open pit to generate a 7-year mine life at an average annual production rate of slightly over 300,000 ounces of palladium. The underground feasibility study’s base case generates approximately C$92 million of cumulative pre-tax cash flow at a palladium price of US$325 per ounce and projected operating costs of approximately US$152 per ounce of palladium after by-product metal credits. Capital costs for the underground development are estimated at C$40 million for direct and indirect costs and working capital.

Mining equipment accounts for an additional C$15 million of capital costs and the Company plans to finance this equipment through a vendor lease program. Construction of the underground mine is planned to commence in May 2004 with first ore production expected in the third quarter of 2005. The underground operation will operate together with the open pit operations and when fully operational it will contribute approximately 750,000 tonnes of mill feed per year.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.