BHP Billiton Complete Hillside Expansion Ahead of Schedule

BHP Billiton officially opened their expanded Hillside plant at Richard’s Bay in South Africa. The inauguration ceremony was attended by Deputy President Jacob Zuma, members of the BHP Billiton Board and other dignitaries.

The expansion project was completed in 20 months, a full 6 months ahead of schedule. It was also completed for US$38 million less than the US$449 million budget figure.

The expansion works consisted of increasing the plant’s output by 25% or 132,000 tonnes per annum. In doing so a third potline had to be constructed, as well as an anode baking furnace, additional casting facilities and additional infrastructure.

For more information on aluminium, click here.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.