Posted in | News | Ceramic Materials | Minerals

Alcan Expects Its Gove Alumina refinery Expansion Project to Cost $2.3 Billion

Alcan has updated its cost estimate and start-up schedule for the Gove alumina refinery expansion and upgrade in the Northern Territory of Australia, reflecting progress in Q4 2006, additional tie-in requirements and weather-related delays. The Company has revised its cost estimate to US$2.3 billion and moved the start-up date from the first to the second quarter of 2007.

“Despite extremely tight market conditions in Australia for labour and materials, the project will deliver positive results by significantly improving Alcan’s cost position and capacity in alumina,” said Jacynthe Côté, President and Chief Executive Officer, Alcan Bauxite and Alumina. “In addition to extremely challenging Australian market conditions, cost impacts include additional tie-in integration work that was determined necessary as the expansion neared completion, the appreciation of the Australian dollar, and severe weather conditions that resulted in late delivery of several large pre-assembled modules (PAMs),” Côté added.

The project was approved in September 2004 and is approximately 95 percent physically complete, with estimated capital spending of US$400 million for 2007. It will increase the refinery's capacity to 3.8 million tonnes per year and is expected to bring Alcan’s internal alumina production capacity into balance with current requirements, and reduce cash costs at Gove by US$30 per tonne.

Project equipment commissioning began in the late third quarter of 2006 and is progressing well. Expanded production ramp-up will start progressively during the second quarter of 2007 and continue through the first quarter of 2008, at which time the refinery is expected to reach its nameplate capacity. Saleable production in 2007 is forecast to be between 2.3 and 2.4 million tonnes, representing an increase of about 500,000-600,000 tonnes compared to 2006’s level of 1.8 million tonnes.

“The Gove project is similar to a number of major construction projects in Australia in having been impacted by increased costs as well as schedule delays,” said Côté. Early in the project, having anticipated tight market conditions and to overcome issues related to the remote location, Alcan implemented an innovative PAM strategy, which entailed a substantial portion of plant components being fabricated in PAM yards off-site and shipped to Gove ready for installation. “Alcan’s PAM strategy partially mitigated the tight Australian market conditions but was unable to offset all cost and scheduling challenges,” concluded Côté.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.